CMS Muon Endcap CSC Mass Production AFEB Delivery

blue_ball.gif Introduction.

The delivery status of the Anode Front End Boards (AFEB) to the Final Assembly and Test (FAST) sites at the University of Florida (UF), the University of California Los Angeles (UCLA), the Petersburg Nuclear Physics Institute (PNPI,Gatchina, Russia) and the Institute of High Energy Physics (IHEP,Beijing,China) is being monitored on this page. The boards have been tested and ceritified on the CMU test stand at Fermilab (test results). For each shipment the number of boards is given along with the key parameters of the boards (see list of parameters). The parameters of all boards delivered to each site are presented in the corresponding list of parameters and in Fig. 1 - Fig. 3 in the board ID ascending order.
blue_ball.gif List of figures (description). List of parameters (description).
blue_ball.gif More details available from AFEB (database) at CERN (maintained by I.Vorobiev of CMU, Igor.Vorobiev@cern.ch).
blue_ball.gif Description of the files (th*.out, rt*.out, mt*.out) in database at CERN.

blue_ball.gif AFEBs for FAST site at UF.

Shipment # Date # of boards Parameters
1 Oct. 2, 2001 124 List
2 Jan. 25, 2002 539 List
3 May 16, 2002 360 List
4 December, 2002 42 List
5 January, 2003 1008 List

Total # of boards Parameters Qthr, Noise etc Resolution time Propagation and slewing time
2071 * List Fig. 1 Fig. 2 Fig. 3

* - excluding first entries for 2 boards returned to UF after repair

blue_ball.gif AFEBs for FAST site at UCLA.

Shipment # Date # of boards Parameters
1 Oct. 2, 2001 124 List
2 Jan. 23, 2002 535 List
3 May 10, 2002 360 List
4 January, 2003 9 List
5 January, 2003 1005 List

Total # of boards Parameters Qthr, Noise etc Resolution time Propagation and slewing time
2024 * List Fig. 1 Fig. 2 Fig. 3

* - excluding first entries for 9 boards returned to UCLA after repair

blue_ball.gif AFEBs for FAST site at PNPI.

Shipment # Date # of boards Parameters
1 Jan. 28, 2002 1008 List
2 Mar. 28, 2002 1152 List
3 April, 2003 1152 List
4 March, 2004 1438 List

Total # of boards Parameters Qthr, Noise etc Resolution time Propagation and slewing time
4750 List Fig. 1 Fig. 2 Fig. 3

blue_ball.gif AFEBs for FAST site at IHEP.

Shipment # Date # of boards Parameters
1 Mar. 28, 2002 1584 List
2 Sep. 12, 2002 1427 List

Total # of boards Parameters Qthr, Noise etc Resolution time Propagation and slewing time
3011 List Fig. 1 Fig. 2 Fig. 3

blue_ball.gif AFEBs for FAST site at CERN.

Shipment # Date # of boards Parameters
1 April, 2003 144 List
2 April, 2004 144 List

Total # of boards Parameters Qthr, Noise etc Resolution time Propagation and slewing time
288 List Fig. 1 Fig. 2 Fig. 3

blue_ball.gif Total delivery to all FAST sites - 12144 AFEB boards.
- List of 12128 boards, updated on July 31, 2009.
- Boards not listed (the boards, not listed in shipping lists, but delivered and installed on chambers).

blue_ball.gif The AFEB boards and CSC chambers (summary, Apr. 26, 2004).

Chamber type FAST site Chambers in CMS detector + (spare) AFEBs per chamber AFEBs on all chambers AFEBs delivered to FAST sites AFEBs on shelf at FNAL
ME1/2 IHEP 72 + (2) 24 1776    
ME1/3 IHEP 72 + (2) 12 888    
Subtotal IHEP 144 + (4)   2664 3011  
ME2/1 PNPI 36 + (2) 42 1596    
ME3/1 PNPI 36 + (2) 36 1368    
ME4/1 PNPI 36 + (2) 36 1368    
Subtotal PNPI 108 + (6)   4332 4750  
ME23/2 UF 72 + (3) 24 1800 2071  
ME23/2 UCLA 72 + (3) 24 1800 2024  
Subtotal UF/UCLA 144 + (6)   3600 4095  
  CERN       288  
TOTAL   396 + (16)   10596 12144  

Total AFEBs (delivered + on shelf) = 12144.


CMU CMS home page
Last modified: Tue July 20 17:30:00 CST 2004